Dredging Consultants

As dredging consultants, we provide advice, knowledge and input on all aspects of the dredging process. These services are always delivered with economic, social and environmental benefits as the primary targets.

Exo facilitates the development of ‘capital’ and ‘maintenance’ dredging operations. This includes project design, development, licencing & permitting applications, site management and environmental monitoring.

Generally a dredging process involves much more than just the dredging activity alone, therefore the range of services is equally extensive. With our international experience, Exo as dredging consultants, provide an insight into a multitude of solutions.

 

WHY CHOOSE EXO?

With our previous track record of working in heavily protected environments, Exo can provide innovative solutions to support any dredging project. With sustainability at the heart of what we do, we look to provide nature based solutions that are both cost effective and environmentally beneficial.

We have a wide range of dredging services including: Beneficial use of dredged material, Dredging innovation, Equipment selection, Budget estimates and Site supervision.

Exo Environmental can support you throughout your project, from consultation to delivery. Please see below to learn more about the projects we have been involved with.

 

Case Studies

  • During the first phase of the Year 2 work package, Royal Smals were commissioned to use their Cutter Suction Dredger (CSD) “Phoenix” to dredge approximately 12,000m3 from Brightlingsea Creek South Channel. This material was pumped up to 1.7km and used to fill the St Osyth borrow pits. These twenty three (23) pits, approximately 30x30x1.5m in size, were originally excavated in the 1960’s in order to strengthen the local coastal flood defences following the 1953 floods. A series of connecting excavations, dams and drop-board sluice gates were installed by subcontractors, Miles Water Engineering, whilst a series of “Y-“ unions and valves allowed the close control of the pumped dredge material, in order to achieve maximum fill and storage volumes.

    The dredging and restoration works were carried out over three successive neap tide periods, to limit the potential for erosion during high springs, with Exo providing site management services throughout. This included coordination of works between the harbour, dredging and restoration teams, liaising with both contractors and members of the public to ensure understanding and encourage support of the project and to confirm all works and mitigation measures put in place were adhered to.

    Inevitably, whilst undertaking a complex operation in a logistically challenging and high risk intertidal environment, problems can arise as a result of unforeseen or uncontrollable circumstances. We employ an adaptive management strategy to our dredging and restoration projects, as recommended by the Central Dredging Association (CEDA), to combat and allow the project to remain robust to such uncertainty. Exo’s site management and expertise allowed any minor issues to be solved efficiently enabling the project to be delivered on time, within budget and with zero harm to people and the environment.

  • Exo Environmental were appointed Principal Designer and Project Manager of a 4 year dredging and restoration project by the Brightlingsea Harbour Commissioners. This project aimed to remove 53,000m3 of accumulated sediment from within the historic Brightlingsea Harbour and beneficially reuse the majority of the arising material to restore 5ha of local intertidal and saltmarsh habitat.

    Due to the quality and extent of the local habitats and the rich biodiversity they support, the site is located within several national and international designated sites, including a Marine Conservation Zone (MCZ) that specifically targets the preservation of the local Native Oyster (Ostrea edulis) populations and the biogenic reef habitats this species creates.

    Under the conditions of the marine licence, the temporal impact of the dredging works on benthic fauna community composition, particularly with regards to monitoring recolonisation and recovery of the local populations within the dredge areas, required monitoring and assessment. To aid interpretation and to monitor rates of sediment accumulation within the Creek, particle size distribution (PSD) was also assessed.

    To achieve this, Exo conducted repeated surveys of the Year 1 dredge areas immediately following cessation of the dredging works and at regular intervals over a 32 week period using a Day Grab deployed from the Exo Surveyor survey vessel. Although species richness and abundance decreased following dredging activity as expected, recovery of benthic populations was observed over the survey period and corroborated recovery times of estuarine species recorded in existing literature.

  • The River Parrett and River Tone on the Somerset Levels are well known for their high risk of flooding, with prolonged flood events becoming increasingly worse in recent years. In 2012, it was estimated that the dredging of approximately 160,000m3 of sediment would significantly reduce the risk and magnitude of flood events and their associated impacts. However, the initial cost calculations were deemed too large and ineligible for standard national funding schemes, thereby rendering the project not unfeasible.

    Somerset Dredging

    Exo Environmental provided advise to both the IDB and the EA on innovative dredging solutions that could potentially provide significant cost saving and reductions in levels of nuisance. Following the latest significant flood event dredging was carried out with significant political pressure.

    Exo Environmental continued after 2014 with providing advice on dredging the River Brue in relation to dredging methodology, licensing, cost saving methods and delivery.

  • Waterside Marina is situated within a high end riverside residential complex, within Brightlingsea Harbour on the River Colne Estuary in Essex, UK, and provides moorings and shore side facilities for recreational vessels and boat owners. In 2015, 11,000m3 of accumulated sediments were removed during a major dredging campaign, with the arising sediments being dispersed on the ebb tide. Following this work, the Brightlingsea Harbour has taken responsibility for the site, which includes undertaking regular maintenance dredging to prevent the marina from silting up in the future.

    To monitor siltation rates and identify target areas to focus maintenance dredging efforts, a survey was undertaken. However as the season was in full swing with high numbers of moored vessels present which limited access throughout the marina, whilst the surrounding sheet piling and high rise residential blocks satellite reception of the bathymetric and topographic GNSS positioning system was not 100%.

    To overcome this issue, a combination of bathymetric and topographic survey techniques were employed to achieve the best possible results. An initial bathymetric survey was undertaken from the Exo Surveyor survey vessel in all accessible areas, subject to satellite coverage. To obtain data in areas where satellite reception was available but access was limited, a centimeter accurate GNSS topographic system on a sounding rod was deployed. In areas where both access and satellite reception were limited, a manual measurement using a graduated rod was taken to ensure 100% coverage of the marina.

  • Beccles Yacht Station and Boat Dyke has silted up over the years due to run off related sources from the main river and the main town drain. The accumulated silt had to be removed to allow for safe navigation as well improve conveyance of the drainage system. Exo were appointed to design and manage the desilting works, including site investigations (Preliminary ecological survey, bathymetric survey and sediment sampling followed by analysis), licence applications (MMO, EA, BA and NE), facilitate a tender and project manage the project throughout. The project was successfully completed in November 2021, and included dredging under D1 licence (EA), Marine licence (MMO) and Broads Works permit with a bank side long reach excavator. The dredged material was dewatered in temporary lagoons before it was transported to a spreading site under a SR2010 No.4 Landspreading licence (EA). The spread and cultivated dredged material will be sown in as a wildflower meadow to improve biodiversity of the the grass swards.

If you have any queries at all, please don’t hesitate to get in contact with us: enquiries@exo-env.co.uk.